ISTQB Foundation Level Certification Software Testing - 13

371. Link Testing is also called as :
a) Component Integration testing
b) Component System Testing
c) Component Sub System Testing
d)Maintenance testing

372.
Rule 1 Rule 2 Rule 3 Rule 4
Conditions
Indian resident? False True True True
Age between 18 – 55? Don't care False True True
Married? Don't Care Don't Care False True
Actions
Issue Memebership? False False True True
Offer 10% discount? False False True False
A.TC1: Anand is a 32 year old married, residing in Kolkatta.
B.TC3: Attapattu is a 65 year old married person, residing in Colombo.
a. A – Issue membership, 10% discount, B – Issue membership, offer no discount. B
b. A – Don’t Issue membership, B – Don’t offer discount. C
c. A – Issue membership, no discount, B – Don’t Issue membership.
d. Issue membership, no discount, B- Issue membership with 10% discount.

373. Methodologies adopted while performing Maintenance Testing:-
a) Breadth Test and Depth Test
b) Retesting
c) Confirmation Testing
d) Sanity Testing

374. Which of the following is true about Formal Review or Inspection:-
i. Led by Trained Moderator (not the author).
ii. No Pre Meeting Preparations
iii. Formal Follow up process.
iv. Main Objective is to find defects
a) ii is true and i,iii,iv are false
b) i,iii,iv are true and ii is false
c) i,iii,iv are false and ii is true
d) iii is true and I,ii,iv are false

375. The Phases of formal review process is mentioned below arrange them in the correct order.
i. Planning
ii. Review Meeting
iii. Rework
iv. Individual Preparations
v. Kick Off
vi. Follow Up
a) i,ii,iii,iv,v,vi
b) vi,i,ii,iii,iv,v
c) i,v,iv,ii,iii,vi
d) i,ii,iii,v,iv,vi

376. Consider the following state transition diagram of a two-speed hair dryer, which is operated by
pressing its one button. The first press of the button turns it on to Speed 1, second press to Speed 2 and
the third press turns it off.
Which of the following series of state transitions below will provide 0-switch coverage?
a. A,C,B
b. B,C,A
c. A,B,C
d. C,B,A

377. White Box Techniques are also called as :-
a) Structural Testing
b) Design Based Testing
c) Error Guessing Technique
d) Experience Based Technique

378. What is an equivalence partition (also known as an equivalence class)?
a) A set of test cases for testing classes of objects
b) An input or output range of values such that only one value in the range becomes a test case
c) An input or output range of values such that each value in the range becomes a test case
d) An input or output range of values such that every tenth value in the range becomes a test case.

379. The Test Cases Derived from use cases
a) Are most useful in uncovering defects in the process flows during real world use of the system
b) Are most useful in uncovering defects in the process flows during the testing use of the system
c) Are most useful in covering the defects in the process flows during real world use of the system
d) Are most useful in covering the defects at the Integration Level

380. Exhaustive Testing is
a) Is impractical but possible
b) Is practically possible
c) Is impractical and impossible
d) Is always possible

381. Which of the following is not a part of the Test Implementation and Execution Phase
a) Creating test suites from the test cases
b) Executing test cases either manually or by using test execution tools
c) Comparing actual results
d) Designing the Tests

382. Which of the following techniques is NOT a White box technique?
a) Statement Testing and coverage
b) Decision Testing and coverage
c) Condition Coverage
d) Boundary value analysis

383. A Project risk includes which of the following :
a) Organizational Factors
b) Poor Software characteristics
c) Error Prone software delivered.
d) Software that does not perform its intended functions

384. In a risk-based approach the risks identified may be used to :
i. Determine the test technique to be employed
ii. Determine the extent of testing to be carried out
iii. Prioritize testing in an attempt to find critical defects as early as possible.
iv. Determine the cost of the project
a) ii is True; i, iii, iv & v are False
b) i,ii,iii are true and iv is false
c) ii & iii are True; i, iv are False
d) ii, iii & iv are True; i is false

385. Which of the following is the task of a Tester?
i. Interaction with the Test Tool Vendor to identify best ways to leverage test tool on the project.
ii. Prepare and acquire Test Data
iii. Implement Tests on all test levels, execute and log the tests.
iv. Create the Test Specifications
a) i, ii, iii is true and iv is false
b) ii,iii,iv is true and i is false
c) i is true and ii,iii,iv are false
d) iii and iv is correct and i and ii are incorrect

386. The Planning phase of a formal review includes the following :-
a) Explaining the objectives
b) Selecting the personnel, allocating roles.
c) Follow up
d) Individual Meeting preparations

387. A Person who documents all the issues, problems and open points that were identified during a
formal review.
a) Moderator.
b) Scribe
c) Author
d) Manager

388. Who are the persons involved in a Formal Review :-
i. Manager
ii. Moderator
iii. Scribe / Recorder
iv. Assistant Manager
a) i,ii,iii,iv are true
b) i,ii,iii are true and iv is false.
c) ii,iii,iv are true and i is false.
d) i,iv are true and ii, iii are false.

389. Which of the following is a Key Characteristics of Walk Through
a) Scenario , Dry Run , Peer Group
b) Pre Meeting Preparations
c) Formal Follow Up Process
d) Includes Metrics

390. What can static analysis NOT find?
a) the use of a variable before it has been defined
b) unreachable (“dead”) code
c) memory leaks
d) array bound violations

391. Incidents would not be raised against:
a) requirements
b) documentation
c) test cases
d) improvements suggested by users

392. A Type of functional Testing, which investigates the functions relating to detection of threats, such as
virus from malicious outsiders.
a) Security Testing
b) Recovery Testing
c) Performance Testing
d) Functionality Testing

393. Which of the following is not a major task of Exit criteria?
a) Checking test logs against the exit criteria specified in test planning.
b) Logging the outcome of test execution.
c) Assessing if more tests are needed.
d) Writing a test summary report for stakeholders.

394. Testing wherein we subject the target of the test , to varying workloads to measure and evaluate the
performance behaviors and ability of the target and of the test to continue to function properly under
these different workloads.
a) Load Testing
b) Integration Testing
c) System Testing
d) Usability Testing

395. Testing activity which is performed to expose defects in the interfaces and in the interaction between
integrated components is :-
a) System Level Testing
b) Integration Level Testing
c) Unit Level Testing
d) Component Testing

396. Static analysis is best described as:
a) The analysis of batch programs.
b) The reviewing of test plans.
c) The analysis of program code.
d) The use of black box testing.

397. One of the fields on a form contains a text box which accepts alpha numeric values. Identify the Valid
Equivalence class
a) BOOK
b) Book
c) Boo01k
d) book

398. Reviewing the test Basis is a part of which phase
a) Test Analysis and Design
b) Test Implementation and execution
c) Test Closure Activities
d) Evaluating exit criteria and reporting

399. Reporting Discrepancies as incidents is a part of which phase :-
a) Test Analysis and Design
b) Test Implementation and execution
c) Test Closure Activities
d) Evaluating exit criteria and reporting

400. Which of the following items would not come under Configuration Management?
a) operating systems
b) test documentation
c) live data
d) user requirement document

Post a Comment

أحدث أقدم